UfiSpace S9501-28SMT Gateway Router Installation Guide
9 Connecting Power
DC Version
1. Ensure there is enough power to supply the system.
The maximum system power consumption is 96.9 watts. It is recommended to ensure that
enough power is reserved from the power distribution system before installation. Also, please
ensure that both PSUs have been properly installed before powering up the equipment, as the
S9501‐28SMT is designed to support 1 + 1 power redundancy.
2. Attach the power cable.
Locate the DC power screw‐type terminal block on the DC PSU. Attach the UL 1015, 14 AWG DC
power cable (not provided within the package contents) to the DC inlet connector on the PSU.
Dangerous voltage!
Must be powered off before removing!
Verify that all electrical connections are grounded before powering on
The DC power source must be reliably grounded
Figure 23.
3. Tighten the screws to the specified torque.
Tighten the screws to a torque value of 7.0+/‐0.5kgf.cm. If the torque is not enough, the lug
will not be secure and may cause malfunctions. If the torque is too much, the terminal block or
lug may be damaged.
Figure 24.
S9501‐28SMT Hardware Installation Guide | 16
| General | Details |
|---|---|
| Name | UfiSpace S9501-28SMT Gateway Router Installation Guide |
| Make | UfiSpace |
| Language | English |
| Filetype | PDF (Download) |
| File size | 0.77 MB |
If you have any questions regarding UfiSpace S9501-28SMT Gateway Router Installation Guide, please ask here and describe the problem in detail.

UfiSpace S9500-30XS Gateway Router Installation Guide

ufiSpace S9600-72XC Router Installation Guide

UfiSpace S9600-64X 100G Aggregation Router Installation Guide

UfiSpace S9600-32X 100G Aggregation Router Installation Guide